In busy periods the wait for a site visit may extend to about three weeks.

Geological and geotechnical reports

A geological and geotechnical report is an expert document describing the composition and geotechnical properties of the foundation soil, the foundation conditions and recommendations for earthworks. It gives the designer and the client the information needed to design the building safely and appropriately.

To prepare a quotation we need:

  • the planned location of the building,
  • the parcel number and cadastral municipality,
  • basic information about the planned building,
  • any available design documentation.

A site plan, floor plans, sections and information on the planned foundations are also helpful. Based on this we review the location and prepare an individual quotation and a proposed date for the fieldwork.

A report is usually prepared before designing a new build, extension, reconstruction, retaining structures or other works in the ground. It may be required by the designer, the structural engineer, the authority or another party involved in preparing the design documentation.

The basic service is a geological and geotechnical report based on a trial pit. The report usually includes:

  • a description of the ground and its geotechnical properties,
  • foundation recommendations for the building,
  • an assessment of infiltration potential,
  • an assessment of landslide and erosion risk and, if needed, proposed measures.

Two additional services are available by agreement:

  • a soakage test to check the permeability of the ground,
  • sizing of a soakaway or detention tank.

We recommend checking the need for additional services with your designer, depending on the planned stormwater drainage and any requirements of the relevant approving authorities.

The assessment includes a review of:

  • the slope and shape of the terrain,
  • the geological composition of the ground,
  • surface water and groundwater,
  • any signs of sliding, erosion or other instability.

Based on the findings, building conditions are set and, if needed, additional investigations, design changes or protective measures are recommended.

Site investigations

At the agreed spot an excavator operator digs a trial pit, and we inspect the ground, describe the individual layers and take measurements if needed. The pit is usually about 70–80 cm wide and up to about 3 m deep, or down to firm ground. Inspecting one pit usually takes about 45–60 minutes.

In a trial pit the geologist inspects the soil layers directly and, if needed, takes samples and carries out a soakage test. With DPL / DPSH probing, no excavation is needed: we measure the resistance of the ground to the penetration of a cone with depth.

Both options can be a suitable basis for a geological and geotechnical report for ordinary residential buildings. The choice depends on the client's needs, the designer's requirements and any requirements of the relevant authorities.

The excavator and operator are usually arranged by the client. If needed we can pass on a contractor's contact, but the client agrees the date, access and price of the excavation directly with the operator. We send instructions for the pit in advance.

The trial pit is usually dug just at the edge of, or directly next to, the planned foundations. We avoid digging where the foundations will later be built. The exact spot is usually easiest to decide on arrival, once we see the actual conditions, the access for the excavator and the planned position of the building.

On sloping ground two pits may be needed, one higher up and one lower down.

Not necessarily. If the pit location, access and date are clearly agreed in advance and the excavator operator is on site, we can carry out the visit without the client. We recommend attending if the position of the building or the pit is not clearly marked on site.

Infiltration and drainage

The permeability coefficient describes the ability of the ground to let water through. A higher value means more permeable ground; a lower value means slower seepage and usually poorer conditions for infiltration.

The value can be used as one of the inputs for sizing a stormwater drainage system.

We assess infiltration potential from the ground conditions and a soakage test carried out in the trial pit. During the test we monitor how fast the water level drops and use this to estimate the permeability of the ground. The result shows whether infiltration is suitable on the site and is the basis for sizing a soakaway.

The size of a soakaway depends on:

  • the permeability of the ground,
  • the size of the contributing roof and paved areas,
  • the expected volume of stormwater,
  • the space available and constraints on the site.

If infiltration is not effective enough or not feasible, a detention tank, flow restrictor or another suitable solution for controlled drainage can be designed, depending on the project.

A soakage test checks the permeability of the ground and shows whether it is suitable for stormwater infiltration.

The client should check with their designer:

  • whether a soakage test is needed for the planned drainage,
  • whether the Slovenian Water Agency requires it.

The test is important mainly when a soakaway or another stormwater infiltration system is planned.

How we work together and preparing documents

We usually schedule the site visit within one to two weeks of the quotation being accepted. In busy periods the waiting time may exceptionally extend to about three weeks. The geological and geotechnical report is usually ready about one week after the site visit.

The price depends mainly on:

  • the location of the building,
  • how demanding and accessible the site is,
  • the type and size of the planned works,
  • the scope of the site investigations needed,
  • any additional services.

Once we receive basic information about the building and the site, we prepare an individual quotation for the specific project.

When the geological and geotechnical report is complete, we first send the client an invoice. Once we receive payment or proof of payment, we send the final report electronically by email, and a printed copy by post to the client's address.